The Energy Regulatory Commission (ERC) issues 24 show-cause orders against 13 power generation companies over electricity outages affecting the Visayas and Mindanao, citing power plant unavailability.

Across the reports, the regulator’s action is framed as enforcement under reliability performance rules. The ERC says it demands “verified explanations” from the firms for exceeding allowable equivalent unplanned outage limits. One outlet adds that the orders were issued on Oct. 14, and notes the ERC had previously issued notices of non-compliance and compliance/explanation orders to other generation companies.

While all accounts agree on the number of show-cause orders and the parties targeted, they differ mainly in emphasis: some foreground the ERC’s move to “clamp down” on specific types of firms, while others focus more directly on the outage area (Visayas and Mindanao) and the regulator’s paperwork step of issuing the SCOs.