A weak rock mass collapses during excavation at Pakistan’s Tarbela Dam 5th Extension Hydropower Project (T-5) on Monday, allowing water from the intake pit to surge into nearby work areas, including an under-construction powerhouse and a tunnel. Wapda declares an emergency, suspends construction, and evacuates workers; no loss of life is reported. Al Jazeera also frames the incident as a partial collapse that produces a water surge at the partially constructed project.
Subsequent reporting from Dawn cites Wapda statements and district administration officials as saying dewatering begins soon after the incident, with the intake pit drained and no further water entering downstream work sites. Dawn also highlights Wapda’s position that there is no threat to the integrity of the main Tarbela Dam or its critical structures, including the main tunnel, tailrace culvert, and switchyard. Engineers and project staff shift toward remedial steps, including plugging the hole with concrete and compiling updates for stakeholders. Dawn reports the civil work and dewatering are likely to be completed within about a week, alongside ongoing assessments of whether any working-area structures were affected.