The National Grid Corporation of the Philippines (NGCP) places the Visayas Grid under a “yellow alert” after outages at several power plants that supply the region. The alert is issued when the operating margin is insufficient to meet the grid’s contingency requirement. NGCP says the yellow alert runs for a limited window in the afternoon to early evening.

Outlets agree the alert is driven by plant outages and affects the Visayas Grid for several hours. One report specifies the timing from 4 p.m. to 7 p.m. and provides figures for available capacity and peak demand, while the other emphasizes the alert’s duration on the prior day without additional technical detail. Both frame the move as part of NGCP’s grid advisories intended to manage contingency needs during reduced operating capacity.