Mumbai’s first large-scale waste-to-energy plant at the Deonar dumping ground is nearing completion, with construction reported as 93% done. The Brihanmumbai Municipal Corporation (BMC) plans to begin trial runs in December, with the facility expected to become operational in early 2027.

The project, valued at about Rs 648 crore, is designed to process roughly 600 tonnes of fresh municipal solid waste per day and produce up to eight megawatts of electricity. Outlets also note that delays from earlier deadlines stem from logistical issues, changes to proposed power capacity, and pending statutory clearances.

Coverage frames the same core timeline and technical outline, while some reports include additional operational and regulatory context. One outlet adds that the trial period is expected to last one to two months and that, after trials, the BMC would seek approval from the Maharashtra Electricity Regulatory Commission to sell generated power, potentially with tariff figures still under discussion.