Google is building its first data center in Wyoming, a large long-term investment reported as worth about $17 billion near Cheyenne. Multiple outlets say the project is tied to new generation and power arrangements intended to supply the facility with electricity.

Quartz and The Next Web both describe how the data center’s power will be sourced largely from natural gas, including a 702-megawatt fuel cell plant. They also say carbon capture is planned for the associated emissions, with the goal described as storing most emissions underground. The way power and emissions controls are presented is a central part of the story’s context, linking the data center expansion to energy sourcing and carbon management.

Taipei Times reports the basic development—that Google will build a Wyoming facility—but provides less detail in the provided summary about the power source, plant size, or carbon capture. Overall coverage focuses on the location, scale of investment, and the stated approach to powering the facility and managing emissions.