Mumbai’s Brihanmumbai Municipal Corporation (BMC) is revising the estimated cost of the Andheri–Goregaon cable-stayed bridge after a conflict is identified with Tata Power’s 110-kV transmission line and towers. Multiple outlets report the project cost increases to about ₹709.16 crore, driven by the need to relocate the power infrastructure. BMC approves additional funds for the relocation, and Tata Power is set to carry out the specialized work.
The bridge is planned to connect the Millat Nagar–Lokhandwala Complex area in Andheri West with Bhagat Singh Nagar in Goregaon West across Goregaon Creek, providing an alternative north–south route meant to ease traffic congestion in nearby corridors. Coverage also notes delays linked to land and mangrove-related availability, and that earlier preliminary works—including environmental clearances and geotechnical and design activities—were carried out while construction was held up.
Outlets align on the revised budget and the cause—transmission infrastructure obstruction—but differ slightly in how they describe the timing and procedural steps. The BMC is reported to consider the proposal through its Standing Committee for final approval, after the relocation planning and reviews.