ADNOC Gas says the Habshan gas complex in Abu Dhabi—the UAE’s main hub that supplies gas across the country—is operating at reduced levels following attacks. The company reports the site is currently at about 60% capacity and is working to increase output as restoration efforts continue. ADNOC Gas states it is targeting roughly 80% restoration by the end of 2026. The company then plans to bring the complex back to full capacity in 2027, indicating a phased recovery schedule rather than an immediate restart.
While the reports agree on the complex involved and the restoration timeline, they do not add further operational details such as the specific impacts on particular pipelines or processing units beyond the current capacity figures. Both outlets frame the announcement as part of the company’s ongoing restoration work after the attacks, focusing on when normal capacity levels are expected to return rather than on assessments of causation or broader market implications.